While the user can see the "Detail" tab title upon opening Projects, the user will not be able to enter this tab until a STIP ID is selected on the Project Table on the Project tab. Upon selection of the desired project, the user will be toggled to the Detail tab which can be used to view and edit detailed information about the project. This interface contains general, asset, and funding information for the project selected.
If the project originated from the Project Bundler application, the project and asset details will be view-only, but the funding information will be editable. If the project is created through STIP Manager, all information will be editable; however, no asset level details are kept for these projects since they are typically only administrative line items.
General Information
There are ten General information fields in the Detail tab:
| Field | Description |
| Name | This textbox can be used to edit the Project Name; required. |
| Description | This textbox can be used to edit the Project Description; required. |
| STIP ID |
This is the unique identifier for the project. For projects originating in the Project Bundler application, this will be a numeric value. For projects originating in STIP Manager, this ID will be automatically generated using the format S##### beginning with S00001. This field will be view only for all projects. |
| PTS ID | This textbox can be used to enter the PTS ID. |
| Municipality |
This picklist contains the values in the Municipality code list, including "Statewide"; required. For projects originating in Project Bundler, this field will be calculated based on the assets in the Asset table. If all assets are within a single Municipality, this field will display that Municipality; otherwise, this field will display Multiple. |
| Project Manager | This textbox is used to edit the Project Manager name responsible for the project. |
| Investment Type | This picklist contains the values in the Investment Type code list; required. |
| Responsible Agency | This picklist contains the values in the Agency code list (ex. RIDOT & RIPTA); required. |
| Engineering Rank | This numeric field contains the Engineering Rank for the project. |
| Municipal Rank | This numeric field contains the Municipal Rank for the project. |
Asset
There are thirteen Asset information fields in the Detail tab. For projects originating from the Project Bundler application, these fields will be populated and disabled. For projects created in STIP Manager these fields will not be available.
| Field | Description |
| Asset Type | This field contains the type of asset as defined by the Project Bundler. Asset Type will be used in the Location field in all reports. |
| Asset ID | This field that contains the Asset ID as defined by the Project Bundler. Asset ID will be used in the Location field in all reports. |
| Asset Name | This field contains a name for the asset as defined by the Project Bundler. Asset Names will be used in the Location field in all reports. |
| Facility Carried | This field contains the Facility Carried for the asset. This field is not required for all Asset Types and may contain a N/A value. |
| Municipality | This field contains the municipality boundary that the asset is located within. |
| Functional Class | This field contains the Functional Classification for the asset. |
| Roadway Jurisdiction | This field contains the Roadway Jurisdiction for the asset. |
| Treatment Type | This field contains the Treatment Type for the asset. |
| FAS | This checkbox indicates whether the asset is on the Federal Aid Highway System. |
| NHS | This checkbox indicates whether the asset is on the National Highway System. |
| SLR | This checkbox indicates whether the asset has a Sea-Level Rise concern. |
| NHF | This checkbox indicates whether the asset is on the Freight Network. |
| EJA | This checkbox indicates whether the asset is within an Environmental Justice Area. |
Funding Information
There are six Funding information fields in the Detail tab. All information in this table originates from the STIP Manager application regardless of how the project was created.
| Field | Description |
| Delete |
This checkbox can be used to mark a funding line item for deletion; multiple funding lines may be selected at the same time. When a row is deleted, a red line will be drawn through all text in the row to indicate a deletion and all funding greater than $0 is modified to $0. To reverse the deletion, the user can unselect the Delete checkbox. Once the desired funding lines have been selected, the user can select the Save Changes button. If the funding has been approved in the STIP, it would first need to go through the Amendment process. Once approved, the funding line will be permanently removed from the system. |
| Phase | This picklist contains all abbreviated values in the Phases code list. The available values are Design (DGN), Construction (CON) and Other (OTH). |
| Program | This picklist contains the available Programs related to the Responsible Agency defined in the General information section. |
| Funding | This field contains the funding abbreviation for all funds applicable to the selected Agency as defined in the Fiscal Constraint section of this document. |
| STIP Window Years |
These fields will contain the amounts programmed for the specified year. The year column will be labeled such that the first year will be the first year of the STIP window. The user is allowed to view previous and future years by selecting the arrows to the left and right of the first and last year. Only current and future years can be modified, previous years shown are for historical purposes only. |
| Total | This field will be view only and will be the sum of all programmed amounts for the funding line item, including any funding outside the window. |
The user can add a funding line by clicking the "Add New" link below the Funding Table. This selection will generate a new, blank line for the user to populate. The user may also select any funding row to edit its content.
Below the funding table, there are also two additional summary rows: Sub-Total and Total Net Changes. These are described in the table below.
| Field | Description |
| Sub-Total | This row is a sum of all amounts for each Year and Total column. |
| Total Net Changes | This row will report the difference between the pending Sub-Total amount and the previously approved Sub-Total amount (new Sub-Total - previous Sub-Total). |
A Fiscal Constraint table will also be available in the Funding Information section below the Funding Table. This table's information is geared toward the Program or Funding selected in the "Target" picklist at the top right of the interface. The Fiscal Constraint table will show the Program or Funding Target, Total Programmed, and Balance (Target – Programmed amounts) for each year in the STIP window. The titles for these summary lines will dynamically change based on the selection in the Target picklist. For example, if "Active Transportation Program" is selected in the Target picklist, the titles for the rows will be Active Transportation Program Target, Active Transportation Program Programmed, and Active Transportation Program Balance. If the user adjusts the STIP window to the right or left in the Funding table, the Fiscal Constraint table will also be updated to reflect the corresponding values.
Edits
Any edits made to a project must be processed through the "Rules Engine" to determine if it requires approval in the Amendments & Adjustments workflow. All changes will be presented in a pop-up window along with the type of change that was triggered to give the user an opportunity to confirm the actions before moving on.
In the pop-up, System Administrators will have the ability to modify the type of change that was triggered by selecting the Type picklist. For all other users, this field will be disabled. Double-clicking a row in the Pending Changes table will display the Rules table and highlight the specific rule that determined the Change Type. When Save Changes is selected, the window will automatically be closed, and the changes will be highlighted in pink on the Detail tab. When the Cancel button is selected, the pop-up will be closed, and the user has the option to revert the values to their previous values by selecting Discard Changes or modify the changes and save again.