When the Municipality Summary Report is selected, the "Filters (Optional)" section will be populated with the option to select a single municipality or multiple. To select municipalities to specify the report, the user can click on a name in the "Available Municipalities" box, then click "Add >>". This will place it on the "Included Municipalities" box, indicating its selected status. To remove a previously selected municipality, the user can click on a name in the "Included Municipalities" box, then click "<< Remove". If no municipalities are chosen, the report will display all projects in all municipalities. There will also be an optional checkbox for this report: Include Funding Detail. If this checkbox is selected, the report will include an additional "Funding Category" column.
To generate the report, the user must select either "Open as PDF" or "Open in Excel." In the report, results will be grouped alphabetically by Municipality and sorted by STIP ID. The columns in this report are:
| Column | Description |
| STIP ID | The unique identifier for the STIP project as shown on the Project Detail tab. |
| Name | The name for the STIP project as shown on the Project Detail tab. |
| Program | The program that the project falls under. |
| Funding Category | The funding category assigned to each funding line. This column will only be included if the "Include Funding Detail" checkbox was selected on the Standard Reports interface. |
| STIP Window Years | These columns will contain the amounts programmed for each year in the selected STIP window. |
| STIP Total | This column will be the sum of all programmed amounts for the funding line item. |
| Remaining Cost | This column will be the sum of all programmed amounts for the funding line item beyond the selected STIP window. |
NOTE: If a project is located within multiple municipalities, an entry will be included in each of the appropriate municipality sections.